Industrial complex - Construction Status
Project Overview
This project aims create a knowledge-creating, eco-friendly industrial hub to shepherd the development of the Saemangeum area and actively respond to the economic growth in the Pan-Yellow Sea Region.
- To develop the area into an agglomeration town with national flagship industries, new growth engine projects, and related research institutions
- To introduce testing and R&D functions for Marine engineering, aviation, energy, and convergence technologies as well as advanced urban service functions
Land Use Plan
- Industrial facilities
- Green space
- R&D facilities
- Schools
- Central commerce
- Waste treatment facility
- Detached houses
- Cultural Center (Eco Center)
- Parks
- Bike-only paths
- Public offices
- Business (general)
- Supply facilities
- Commerce building apartments
- Gas stations
- Public apartments
- Pedestrian roads
- Plazas
- Distribution business facilities
- Neighboring living facilities
- Business (international)
- Wastewater pumping station
- Support facilities
- Parking lots
- Multi-family dwellings (townhouses)
- Roads
Scale and Layout
Scale
-
Area
41.7k㎡
-
Functions to be Introduced
- Concentration of major industries, new growth engine projects and related research institutions
- Test and R&D functions for marine engineering, aviation, energy, and convergence technologies
- City service functions
Layout
-
1. Saemangeum Industrial Complex
- Comprehensive bonded area (about 1.16 million㎡)
- Occupied by many global companies
-
2. Aviation & Transport Industrial Complex
- To build a new transportation-related industrial research complex
-
3. Convergence Industrial Complex
- An international exchange activity axis centered around the residential, commercial, and international business districts
-
4. Industrial Research Complex
- Creation of an energy and environment complex including the Korean fusion demonstration reactor and artificial photosynthesis research facilities
Key Industries
Reclamation Status
Work Progress by Section
-
As of the end of August 2019, the Industrial Complex (18.5㎢) is divided into 9 reclamation sections with the overall process rate standing at 27.9%*.
*Out of the total project cost of KRW 2.55 trillion, KRW 707.1 billion (including national budget of KRW 47.2 billion) has been spent. -
Out of 9 sections, 4 sections (1, 2, 5, 6) are in progress and 5 sections (3, 4, 7, 8, 9) yet to be launched.
- Section 1 (1.84㎢): Reclamation work completed
- Section 2 (2.55㎢): Reclamation work completed
- Section 5 (1.81㎢): Reclamation work completedSection 6 (1.90㎢): Reclamation in progress (93%)
※ The Ministry of Economy and Finance adjusted the public institutions’ functions (Nov. 2017, the Ownership Steering Committee)
- The SDIA decided to develop the sections that were not kicked off on its own.
* (Previous) Development by private investors → (Present) Development by a project operator (Korea Rural Community Corporation)
Utility status
Ser. No. | Description | Supplier | Capacity | Allowance | Remarks |
---|---|---|---|---|---|
1 | Industrial water |
Intake: Buyeo (Geumgang River) Reservoir: Osikdo, Gunsan-si |
80,000 ton/day | 25,000 |
|
Residential water |
Intake; Yongdam Dam, Jinan-gun Reservoir: Osikdo, Gunsan-si |
14,000 ton / day | 6,000 |
|
|
2 | Wastewater treatment | Gunsan-si Wastewater Treatment Plant | 43,000ton / day | 10,000 |
|
3 | Electricity |
KEPCO Gunjang Substation KEPCO Bieung Substation |
154kV 154kV |
- |
|
4 | Steam (heat) | OCI-SE (cogeneration plant) | 340ton / hr | 303 |
|
5 | Gas | Gunsan City Gas |
70,000㎥ / hr 1,680,000㎥ / hr |
- |
|