Tourism Base Construction - Sinsi-Yami Tourism and Leisure Area Development
Project Overview
Construction of various tourist facilities such as hotels, water parks, golf courses, and marinas to create a global marine resort in the Saemangeum Sinsi-Yami District (1.92㎢)
Project Promotion Direction
Focus on nautical tourism, marine entertainment, and marine leisure & sports experiences
Expected Effects
-
1
Growth into a global tourist destination representing the West Coast
-
2
Construction of a global resort complex with tourism, leisure, and recreation facilities to create new tourism demand at home and abroad
-
3
Promotion of investment in the Tourism and Leisure Site through pioneering Saemangeum projects
Project Summary

-
Location/Land Size
- Sinsi-Yamido-ri, Gunsan-si, Jeollabuk-do
- 1,922,818㎡ (580,000 pyeong)
-
Period
2018-2030 (Earthwork completed by 2025)
-
Budget/Contractors
- KRW 876.8B (KRW 63.8B for earthwork)
- Boseong (49%), Hanyang (46%), Lohas Living (5%)
-
Facilities to be Constructed
Accommodation, leisure, commercial, residential, and public facilities
Progress
- 2017. 9 Business agreement signed
- 2018. 8 Project operator designation
- 2020. 9 Approval/announcement of basic development Schedule
- Plan2021. Phase 1, Sinsido Hotel Construction Kickoff