Project Overview

The Unmanned Autonomous Vehicle Test Bed Construction Project is aimed at creating a huge test stage in the Saemangeum area to test the actual traffic environment for the safety and commercialization of autonomous vehicles.

  • The project is intended to develop the Saemangeum area into a mecca of related high-tech industries by motivating technological development and accelerating commercialization in related industries.

Expected Effects

  • 1
    The Development of Related Industries

    Contributions to the development of various related industries such as agriculture, transportation, and logistics, as well as unmanned vehicles

  • 2
    Job Creation

    Creation of thousands of new jobs in engineering, data analytics, vehicle monitoring, etc.

  • 3
    Regional Economic Development

    Contributions to the economic recovery of the struggling Gunsan region in a significant way

History

  • 2019 Completion of Phase 1, the Commercial Vehicle Driving Test Ground Project
  • 2020 Promotion of Phase 2, the Dyke Road Test Bed Project
    - Preparation of shop drawings
    - Turn-road driving test path
    - Installation of roadside communication equipment, etc.
  • Planned
    2021Phase 3, the Urban Section Demonstration Project

Implementation Plan by Phase

Implementation Plan by Phase(Phase 1, Phase 2, Phase 3)
Phase 1 (2019 / technology materialization) Phase 2 (2020 / technology confirmation) Phase 3 (2021 / technology validation)
Contents Low speed driving (less than 60km/h) High-speed driving on a dedicated automobile road, etc. Commercial service of autonomous vehicles on roads
Test bed Commercial vehicle driving test ground Saemangeum dyke road Saemangeum industrial complex roads
Agency concerned MOTIE, Jeonbuk MOTIE, Jeonbuk SDIA, Jeonbuk, Gunsan-si
Progress Completed in 2019 Kickoff in 2020 Kickoff in 2021
Diagram Driving test (Phase 1)
Dyke road test (Phase 2)
Complex road demonstration (Phase 3)

The Saemangeum ‘Unmanned Autonomous Vehicle Test Bed Construction Project’ consists of three phases, with the first phase (commercial vehicle driving test ground) complete in 2019 and the rest in progress as scheduled.

Implementation Plan by Phase

*Phase 2 (dyke road test bed) is a 20 billion won project, the contract for which the implementation drawings engineering work is signed in October 2020.

공유하기